Can a Developer Cancel an Off-the-Plan Contract in Queensland? Sunset Clauses and Recent Court Decisions

Tower cranes beside an apartment building under construction

Quick answerA developer cannot necessarily cancel an off-the-plan contract just because the sunset date has passed. In Malligan, the Supreme Court held the purchasers’ contracts remained binding, while in CAV Gasworks the Court of Appeal upheld a developer’s termination. The outcome depends on the contract wording, and the rules differ for apartments and land.

Last reviewed: 3 November 2026

Buying property off the plan often involves entering into a contract several years before construction is completed.

During that period, property values may increase substantially. However, if construction is delayed and the contractual sunset date passes, purchasers may face an unexpected situation where the developer seeks to terminate the contract and return their deposit.

For purchasers who have waited years for their property, receiving a refund may be of little comfort if comparable properties have significantly increased in value.

Two recent Queensland decisions demonstrate the importance of the contractual wording governing a developer’s right to terminate: Malligan v Chevron Apartments Pty Ltd; Cantavenera v Chevron Apartments Pty Ltd [2026] QSC 195 and CAV Gasworks Pty Ltd v JYP Jiang Pty Ltd [2026] QCA 221.

Although both concerned off-the-plan apartment contracts, the courts reached different conclusions. These decisions provide important guidance for purchasers and developers concerning sunset clauses in Queensland.

The two cases at a glance

Purchasers succeedAppeal pending

Malligan v Chevron Apartments Pty Ltd [2026] QSC 195

Court
Supreme Court of Queensland
Project
Chevron One, Chevron Island, Gold Coast
Contracts
2021, for $760,000 and $840,000
Key word
“must”
Outcome
Contracts declared valid and binding on 21 August 2026
Developer succeedsCourt of Appeal

CAV Gasworks Pty Ltd v JYP Jiang Pty Ltd [2026] QCA 221

Court
Queensland Court of Appeal (2:1 majority)
Project
Luminare, Newstead, Brisbane
Contract
2017, for a combined $4.2 million
Key word
“cannot”
Outcome
Termination upheld and the approximately $6.1 million award set aside on 30 October 2026

What Is a Sunset Clause in an Off-the-Plan Contract?

A sunset clause allows a party to terminate a contract if a specified event has not occurred by a particular date.

In off-the-plan transactions, that event commonly relates to completion of construction or registration of the subdivision plan. For example, a purchaser may enter into a contract to buy an apartment with a sunset date five years after signing.

If the developer has not completed the relevant requirements by that date, the contract may provide a termination right. However, the passing of the sunset date does not necessarily mean the developer can automatically terminate.

The clause, the developer’s contractual obligations and the applicable legislation must be considered together.

Malligan v Chevron Apartments: Purchasers Successfully Challenge Termination

In Malligan v Chevron Apartments Pty Ltd; Cantavenera v Chevron Apartments Pty Ltd [2026] QSC 195, the Supreme Court of Queensland considered whether a developer could terminate two off-the-plan apartment contracts after their sunset dates had passed.

The proceedings concerned Chevron One, a proposed 40-storey residential development on Chevron Island on the Gold Coast.

In 2021, purchasers entered into contracts for apartments priced at $760,000 and $840,000 respectively. Each contract contained a sunset date five years after its contract date.

When settlement had not occurred, the developer purported to terminate the contracts in April and May 2026. The purchasers challenged those terminations.

Why Did the Word “Must” Matter?

A central issue was clause 10.2. Subject to specified qualifications, the developer was required to “establish the Scheme, register the Plan and effect Settlement” by the sunset date. The obligation was expressed using the word “must”.

The developer argued that the clause should be interpreted as requiring reasonable efforts rather than an obligation to achieve those steps. Justice Freeburn rejected that interpretation.

The Court found that clause 10.2 imposed a positive contractual obligation, subject to the qualifications expressly stated in the contract.

An obligation to complete specified steps by a particular date is not necessarily the same as an obligation merely to use reasonable or best endeavours to achieve them.

Could the Developer Rely on Its Own Failure to Complete?

The Court considered the principle that, unless a contract clearly provides otherwise, a party should not be entitled to rely on its own breach of a primary contractual obligation to bring the contract to an end.

Clause 16 already gave the developer express termination rights in specified circumstances, including development approvals, finance and project viability. Those provisions helped establish how the parties had allocated development risk.

The existence of those express rights did not justify reading down the obligation under clause 10.2 to one of reasonable endeavours.

Justice Freeburn concluded that the contracts did not contain sufficiently clear provisions allowing Chevron to rely on its failure to perform clause 10.2 as a basis for termination in the circumstances.

The decision does not establish that a developer can never terminate after a sunset date. Its significance lies in the interaction between the developer’s positive obligations and its express termination rights.

Could Increased Body Corporate Costs Justify Termination?

Chevron also argued that changes to the development, including increased body corporate contributions and continuing construction, materially prejudiced the purchasers under section 214 of the Body Corporate and Community Management Act 1997 (Qld).

According to Chevron, this gave the purchasers a statutory termination right which, in turn, activated the developer’s reciprocal contractual right under clause 25(c).

The Court rejected the argument. For one apartment, estimated annual body corporate contributions had increased from approximately $5,547 to $7,789 over five years.

The Court considered the nature and practical effect of the changes, including ongoing construction and increased contributions, and was not satisfied that they established material prejudice to the purchasers.

The test was objective, having regard to the particular circumstances of the purchasers. Their subjective views that they were not prejudiced were not determinative.

An increase in anticipated body corporate expenses does not, by itself, establish material prejudice under section 214.

What Was the Outcome?

On 21 August 2026, the Supreme Court declared that both contracts remained valid and binding. The purported terminations were ineffective.

The developer lodged appeals in the Court of Appeal on 16 September 2026. Accordingly, Malligan reflects the position at first instance and may be affected by the appeal’s outcome.

CAV Gasworks v JYP Jiang: Court of Appeal Upholds Developer’s Sunset Termination

The second case concerned the Luminare apartment development in Newstead, Brisbane.

In 2017, JYP Jiang Pty Ltd contracted to buy two proposed sub-penthouse apartments from CAV Gasworks Pty Ltd for a combined $4.2 million.

The contract permitted termination if the developer could not give a specified notice within five and a half years. Although separate titles had been created before the sunset date, the apartments were not ready for settlement.

The developer purported to terminate in April 2023 and subsequently agreed to sell the apartments to other purchasers. The original purchaser challenged the termination.

The Original Supreme Court Decision

On 12 June 2025, the Supreme Court delivered JYP Jiang Pty Ltd v CAV Gasworks Pty Ltd [2025] QSC 134.

The Court initially found that the developer was not entitled to terminate. The purchaser was awarded approximately $6.1 million, including interest. The developer appealed.

The Court of Appeal Reverses the Decision

On 30 October 2026, the Queensland Court of Appeal delivered CAV Gasworks Pty Ltd v JYP Jiang Pty Ltd [2026] QCA 221.

By a majority of two to one, the Court allowed the developer’s appeal and overturned the substantial damages award.

The dispute centred on the meaning of “cannot” in clause 8.3. The purchaser argued that the developer could have given the relevant notice because separate titles had already been created.

However, the majority construed the provision in the context of the developer’s settlement obligations. Clause 8.1 allowed the developer to defer notice until satisfied that its contractual and legal obligations could be completed within 14 days.

Although the titles existed, the apartments were not ready to be handed over. Although the two majority judges reasoned differently, both concluded that the developer was entitled to terminate under clause 8.3.

The Court of Appeal set aside the damages award and dismissed the purchaser’s claim, apart from the existing declaration concerning the deposit. The purchaser was also ordered to pay the developer’s costs of the claim and appeal on the standard basis.

That decision is now the operative appellate authority on the contractual provisions considered in the dispute.

How each dispute unfolded

  1. 2021Purchasers sign contracts with sunset dates five years after the contract date
  2. April and May 2026Developer purports to terminate both contracts
  3. 21 August 2026Supreme Court declares both contracts valid and binding
  4. 16 September 2026Developer lodges appeals in the Court of Appeal
  1. 2017Purchaser contracts to buy two sub-penthouse apartments for $4.2 million
  2. April 2023Developer purports to terminate and later sells the apartments to other purchasers
  3. 12 June 2025Supreme Court finds the termination invalid and awards approximately $6.1 million
  4. 30 October 2026Court of Appeal, by majority, upholds the termination and sets aside the award

Why Did the Two Cases Produce Different Outcomes?

Both disputes concerned developers attempting to terminate off-the-plan apartment contracts. However, their contractual provisions were materially different.

In Malligan, the developer had undertaken a positive obligation to establish the scheme, register the plan and complete settlement by the sunset date, subject to specified exceptions.

In CAV Gasworks, the question was whether the developer could give a particular contractual notice when it was not yet able to complete its settlement obligations.

IssueMalligan [2026] QSC 195CAV Gasworks [2026] QCA 221
Central wordingDeveloper “must” establish the Scheme, register the Plan and effect Settlement by the Sunset Date, subject to clause 16Whether the developer “cannot” give the required notice in the context of its settlement obligations
Court’s approachClause 10.2 imposed a positive obligation; the developer could not rely on its own breach to terminate in the circumstancesThe majority considered the developer’s practical ability to give notice in the wider contractual context
OutcomePurchasers’ contracts declared valid and bindingDeveloper’s termination upheld; damages award set aside
Current positionFirst-instance decision; appeal pendingCourt of Appeal decision delivered 30 October 2026

A sunset clause cannot be interpreted in isolation. Its operation depends on the contract as a whole and the obligations imposed on the parties.

Are Sunset Clauses Different for Vacant Land and Apartments?

Yes. Queensland has different statutory regimes for off-the-plan vacant land and proposed community title lots.

Vacant land

Land Sales Act 1984 (Qld)

Automatic termination
A sunset clause cannot automatically terminate a relevant contract (s 19C)
Developer termination
Generally only with the purchaser’s written consent, a Supreme Court order or another prescribed method (s 19D)
Sunset period
Seller must generally settle within 18 months, or the purchaser may terminate (s 14)
Commenced
22 November 2023
Apartments

Body Corporate and Community Management Act 1997 (Qld)

Automatic termination
The 2023 Land Sales Act restrictions do not apply
Developer termination
Depends on the contract and other applicable law
Purchaser rights
May include section 217B where settlement is delayed beyond the statutory period

Off-the-Plan Vacant Land

The Land Sales Act 1984 (Qld) regulates many sales of proposed residential land lots.

Reforms that commenced on 22 November 2023 restricted developers’ ability to terminate certain off-the-plan land contracts under sunset clauses.

Under section 19C, a sunset clause cannot automatically terminate a relevant contract. Section 19D generally permits developer termination only with the purchaser’s written consent following the prescribed notice process, by Supreme Court order or by another prescribed statutory method.

Off-the-Plan Apartments

The position differs for proposed apartments and other community title lots governed by the Body Corporate and Community Management Act 1997 (Qld).

The 2023 Land Sales Act restrictions do not extend to those contracts. The developer’s termination rights instead depend on the contract and other applicable law.

Apartment purchasers may have separate statutory termination rights under the BCCM Act, including section 217B where settlement is delayed beyond the relevant statutory period.

Whether a purchaser has a right under section 217B, and when that right arises, depends on the terms of the contract and the applicable statutory timeframe. These purchaser protections are distinct from a developer’s contractual termination right.

Read more: Buying Off the Plan in Queensland: Settlement Dates, Delays and Sunset Clauses

What Should Buyers Do if a Developer Issues a Termination Notice?

A purchaser who receives a sunset clause termination notice should not assume the developer is entitled to cancel the contract.

The contract should be reviewed to establish whether the relevant event occurred, whether the developer complied with the notice requirements and whether any qualifications or separate termination rights apply.

Purchasers should preserve the signed contract, disclosure documents and relevant correspondence, including notices concerning extensions and settlement.

Before you respondA purchaser disputing termination should obtain legal advice before responding to the notice, signing a release or accepting a deposit refund, because subsequent conduct may affect the available remedies.

A deposit refund is not necessarily the only issue. Depending on the contract and circumstances, further contractual rights or remedies may be available.

Received a termination notice? Your checklist0 of 5 checked

All done. Act promptly, as your next steps may affect the remedies available to you.

Why Sunset Clauses Should Be Reviewed Before Signing

Off-the-plan contracts may remain on foot for years, during which construction can be delayed and property values may change substantially.

Purchasers should understand whether a sunset clause benefits them, the developer or both parties, and whether the developer must complete specific steps by a particular date or merely use defined endeavours.

These matters are best addressed before signing rather than after a dispute arises.

What Do These Decisions Mean for Queensland Purchasers?

In Malligan, the Supreme Court upheld the purchasers’ contracts, although an appeal remains pending.

In CAV Gasworks, the Court of Appeal upheld the developer’s termination and overturned the approximately $6.1 million damages award.

The different outcomes reinforce the importance of carefully reviewing the contract rather than making assumptions about what happens when a sunset date passes.

Key takeawayA sunset clause is not merely a date in an off-the-plan contract. It is a contractual mechanism that may determine whether a purchaser ultimately receives the property they agreed to buy.

This article provides general information only and does not constitute legal advice. The application of sunset clauses depends on the particular contract, the circumstances and the relevant legislation. Readers should obtain advice about their own circumstances.

How Vojdani Lawyers Can Assist

Vojdani Lawyers advises property purchasers and developers on off-the-plan transactions throughout Queensland.

Our lawyers assist with preparing and reviewing off-the-plan contracts, including sunset clauses and developer termination provisions.

We also advise on the statutory requirements governing proposed residential land and community titles schemes, together with the consequences of delayed registration and settlement.

Where a developer seeks to terminate an off-the-plan contract, we can review the contractual provisions and advise on the parties’ legal rights and available options.